FG to Open Section of Lagos-Calabar Coastal Highway December 12

Lagos Calabar Coastal Highway

The federal government is set to open Section 1 of the 700 km Lagos-Calabar Coastal Highway for public use from December 12 to 17, 2025.

The Minister of Works, Mr Dave Umahi, gave the assurance on Sunday in Lagos during a review of outstanding works on Section 1 of the highway project.

The section 1 is 47.47km long and has six lanes and two carriageways.

Mr Umahi said: “We also set aside April next year to have Section 1 and half of Section 2 fully completed and commissioned,” adding that the contractor handling the project, Hitech Construction Company Limited, had achieved more than 80 per cent of the reinforced concrete pavement.

“We are very grateful to God Almighty for his mercies, and to the President and to the contractor.

“If we are to pay for everything they have done, it will be very difficult to have this job done because there are places we didn’t envisage that we were going to be removing pits up to a depth of 20 metres.

“They had to do that because they are partners in progress for the development of the country.

“We have just about three kilometres to complete the entire sand filling from Ahmadu Bello Way to Eleko Junction, and we are excited at the work and the quality of what has been done,” the former Governor of Ebonyi State, said.

The new Controller of Works in Lagos, Mr Olufemi Dare, told the minister that a lot of settling was ongoing at Chainage 33 of the highway project, praising the contractor for high quality of work.

“Sir, it may interest you to know that the building standing is the palace of this community, and you saved this building, and they are extremely happy,” he said.

On his part, the Managing Director of Hitech Construction Company Limited, Mr Dany Abboud, said that the company would still backfill from Chainage 34 to Chainage 37.

“Dredging is ongoing, we are on track to deliver.

“We are monitoring the settlement in the swampy areas and the water body areas due to the change of alignment,” he said.

The highway, which commenced construction in March 2024, has generated a lot of controversy, with critics raising concern around cost and procurement structure.